Receptkalkyler: En fältstudie av kalkylrecptens precision för byggentreprenören
Umeå University, Faculty of Science and Technology, Department of Applied Physics and Electronics.
2016 (Swedish)Independent thesis Basic level (professional degree), 10 credits / 15 HE creditsStudent thesisAlternative title
Recipes for calculations (English)
Abstract [sv]

Selbergs entreprenad AB är ett byggföretag som bedriver byggverksamhet i Umeå. Inom organisationen bedrivs ett ständigt arbete med erfarenhetsåterföring för att konstant förbättra sin konkurrenskapacitet. Examensarbetet verkar inom ramarna för det arbetet. Företaget tillämpar receptkalkylering för sina kalkyler. Platsgjutning av betongstommar är en återkommande process i deras produktion. Därför finns här ett intresse av att undersöka hur väl recepten stämmer överens med produktionsmetoderna. Kalkylingenjören på företaget har en tes om att företaget har en högre kapacitet än vad recepten anger i kalkylerna.

Syftet med examensarbetet är att optimera förutsättningarna för anbudskalkyler och produktionskalkyler genom kunskapsåterföring.

Målen är att med hjälp av en fältstudie hitta konkreta ändringsförutsättningar i kalkylrecepten för väggar, bjälklag balkonger och trappor, samt presentera verkliga enhetstider jämförda med de kalkylerade.

Fältstudien genomfördes parallellt med en analys av anbudskalkyl och produktionskalkyl för det då pågående byggprojektet ”Lyckoslanten”. Cykler för utförandet av byggdelstyperna identifierades och tider uppmättes två gånger. Mätningen genomfördes genom avstämning med ansvariga yrkesarbetare upp till fyra gånger per dag. Alla produktionsresultat i recepten avstämdes mot de verkliga produktionsmetoderna. Från de uppmätta tiderna beräknades enhetstider för Byggdelstyperna som slutligen jämfördes mot kalkylen.

 

Slutsatsen av studien är:

 

  • Tesen om en högre produktionskapacitet än vad recepten anger kan bekräftas för Byggdelstyperna väggar, bjälklag, balkonger och trappor.

 

  • Recept för Byggdelstypen bjälklag bör justeras på så sätt att man skiljer på valvformtekniker och att produktionsresultatet ”efterbehandling takyta” läggs till.

 

  • För Byggdelstypen ”Prefab trapp” bör namnet förbättras något för att undvika feltolkning, förslagsvis till ”Intern prefab trapp”, och ingående produktions-resultat bör upprättas.

 

  • Receptet för Byggdelstypen balkonger kan användas i sin nuvarande form men namnet bör ändras så produktionsmetoden framgår och tillägg i gemensamma kostnader utföras. Namnförslag ”Intern prefab balkong”

 

  • Vinterklimat har en tröghetseffekt på momenten som inte uppenbart faller in under de gemensamma kostnadsposterna snöröjning och materialtäckning, möjligheter för tillägg på enhetstider under vintertid för berörda Byggdelstyper bör utredas.
Abstract [en]

Selbergs Entreprenad AB is a construction company that runs their construction business in Umeå. The organisation is constantly taking care of experience within the company to improve their ability of competitiveness. This final essay is within those frames. The company uses recipes for calculations. Location moulding of concrete framework is a reoccurring process in their production. The calculee has a thesis that the company have a higher capacity than what the recipes says in the calculations of the building components for the concrete framework.

This essay looks to optimize the conditions for tender calculations and production calculations through feedback.

With the help of a field study, the goal is to find actual conditions of change in the calculation recipes for building components belonging concrete frameworks and present real unit times compared with the calculated unit times for chosen building components.

 

The field study was done parallel with the analysis of the tender calculation and production calculation for the already ongoing building project "Lyckoslanten". Cycles for four building parts was identified and times were measured twice. The measurement was conducted with and supervised by workers in charge up to four times a day. All production results in the recipes was compared to the real production methods. From the measured times, unit times were calculated for the building components that finally were compared to the calculation.

 

The conclusions are as follows:

 

  • The thesis of a higher production capacity in reality is confirmed for the building parts walls, beams, balconies and stairs.

 

  • The recipe for vault should be adjusted in a way that you separate techniques for forms and that the production result “efterbehandling takyta” is added.

 

  • The name ”Prefab trapp” should be changed to “Intern prefab trapp” to avoid misinterpretation and specific production results should be established.

 

  • The recipe for balconies can be used in its current form but the building part name should be changed so that the production method is clear and additions in common costs be done. The name should be changed to “Intern prefab balkong”.

 

  • The winter climate has a slowing effect on the operations that aren´t included in the common costs for snow clearing and covering of material. Possibilities for added unit times during winter should be considered and investigated.
Place, publisher, year, edition, pages
2016. , 28 p.
Keyword [sv]
Kalkyl, receptkalkyl, enhetstid
National Category
Engineering and Technology
Identifiers
URN: urn:nbn:se:umu:diva-119130OAI: oai:DiVA.org:umu-119130DiVA: diva2:918981
External cooperation
Selbergs Entreprenad AB
Subject / course
Byggteknik
Educational program
Bachelor of Science Programme in Civil Engineering
Presentation
2016-03-21, Ta 303, Håken Gullessons väg 20, Teknikhuset, Umeå, 11:00 (Swedish)
Supervisors
Examiners
Available from: 2016-04-12 Created: 2016-04-12 Last updated: 2016-04-12Bibliographically approved

Open Access in DiVA

No full text

By organisation
Department of Applied Physics and Electronics
Engineering and Technology

Search outside of DiVA

GoogleGoogle Scholar
The number of downloads is the sum of all downloads of full texts. It may include eg previous versions that are now no longer available

Total: 43 hits
ReferencesLink to record
Permanent link

Direct link